Total surface area : 8 000 M²
Construction time : 12 Months
Location : Rhône-Alpes / South-east

Architect

CDA Architectes

Status

Completed

Further information

6 000 m² of space with a 2 000 m² extension.

The head office of Nicomatic, a “nugget” of connector technology, was built in two phases. The first phase, in 2007, was the construction of 5,000 m² of factory space and 1,000 m² of offices. The second, which is in progress, includes an extension of the production facility (2 000 m²), offices and car park, as well as the creation of a micro-day care centre. GA was involved in all the stages, from design to construction, and deployed its know-how throughout the division of work, in particular implementing the supply circuits of production tooling.

François Minck

Contact

François Minck

Managing Director, Industry Unit

Title

Fields marked with an asterisk are required. The information gathered via this form is provided to GA’s Communications Department. You are entitled to request from GA the right to access, rectify, erase or enjoy the portability of your personal data under the conditions provided for in the General Data Protection Regulation (Regulation (EU) 2016/679 – Chapter III – Data subject’s rights).

Find out more about managing your data and rights

Thank you for your message. Our teams will address it shortly.

Nicomatic in Bons en Chablais

Nicomatic in Bons en Chablais

To know more